Unitized Curtain Wall

METHOD STATEMENT

1. Contractor / Sub-contractor Details

Contractor:

Sub-Contractor:

AMG – Advanced Manufacturing for Metal & Glass Co.

                        2nd Industrial Area, 16 Street

                        Dammam – 31414, KSA

                        013-812 7776

2. Scope / Summary of Works

This Method Statement is prepared in accordance with the façade work activities and applies to all work activities associated with the installation of the CURTAIN WALL UNITIZED SYSTEM for the project.

3. Programmed Duration of Activities

Detailed project schedule is to be submitted in accordance with the overall project completion schedule date for approval.

4. Management Structure/ Resource Responsibilities

The overall works are to be supervised by AMG Co’s Project Manager who will report to the main contractor’s Construction Managers.

Information and contact detail of the Project Manager is available in the below next section.

5. Communication / Contact Details

Main Contractor Personnel:

AMG Personnel

6. Method Statement

6.1 INTRODUCTION

This Method Statement described the proposed organization, general logistics, and proper installation methodology for the Unitized Curtain Wall and other associated works of AMG for the project.

Coordination and communication are the vital keys for a proper installation, therefore teamwork is essential, and each member of the teams; from (consultant, to contractor, to AMG, and to the rest of the subcontractors must understand the needs and the problems of one another (if there is any) to achieve a smooth and efficient works progression.

The purpose of this method statement is to provide and overall understanding of what the works comprise and to ensure this will be implemented properly and carefully monitored on site daily activities. To ensure smooth operation, this document will be coordinated with the Main Contractor’s overall Construction Program and Planning.

Note: This is a working document, which may be amended from time to time to suit developments within the works package. Also, it should be note that specific Safe System of Work (SSOW) and Risk Assessment (RA) will be develop for each of the activities described in this document and that these in turn will be reviewed prior for undertaking the work.

6.2 KEY RESPONSIBILITIES

PROJECT MANAGER:

DOCUMENT CONTROLLER:

SURVEY TEAM:

SITE ENGINEER:

QA/QC ENGINEER/INSPECTOR:

QS ENGINEER:

HSE ENGINEER / OFFICER:

SITE FOREMAN:

6.3 GENERAL REQUIREMENTS

The area of installation for the UNITIZED CURTAIN WALL panels must be free from any obstruction and other operatives. Slab/Beams edges and masonry opening for Unitized System must be leveled, plumbed, squared and within the required tolerance (Width: ± 10mm | Height: ± 10mm), otherwise the main contractor should rectify the concrete opening and turnover to AMG and checked by QA/QC prior to installation. Heads, jambs, and sill must be true details (application of water proofing applied to required areas). Areas that shall be covered with aluminum frames must be given a smooth finish. Opening must be free of wet concrete works prior to installation of aluminum frames.

All aluminum frames are protected with protective films. And in case unavoidable concrete works are done within one (1) meter of the aluminum frames, contractors involved shall cover the said frames with polyethylene sheets or any protective sheets to avoid damages to the installed materials.

All UCW panels will be delivered in complete set with good quality, and all aluminum sections for Unitized system shall be delivered to site pre-cut, pre-notched, bracketed for both vertical and horizontal frames connection and covered with protective tapes. Fabrication will be supervised and instructed.

A temporary staging area must be made available to AMG where to offload deliveries and from which distribution can be affected. Glass and aluminum shall be hauled and distributed on their designated floors, by means of Hoisting.

6.3.1 METHODOLOGY AND INSTALLATION SEQUENCE

All panels will be produced according to aluminum system supplier and as per the required quality finish.

These items are being checked during and after production according to aluminum  system supplier’s quality control system and specifications.

Production and Fabrication tolerances – Shall be taken into consideration.

Repairs, if required shall be initiated at the factory. However, minor damage may happen during transportation and/or the installation of the panel, subsequently the approved repair procedures approved by the client will apply at the factory and at site.

Unloading, hoisting, and handling stock on site.

CURTAIN WALL UNITIZED PANEL INSTALLATION

6.3.2    MATERIAL PACKING

6.3.3    DELIVERY, HOISTING AND STORAGE

6.4 INCOMING MATERIAL CONTROL

Once installation is in full swing, delivery of materials shall be on a continuous basis assuming that all requests and permits have been pre-arranged prior to any deliveries. Any problem that the jobsite might encounter in relation to deliveries such as an unavailability of the man-material hoist and equipment material hoist or a temporary staging area shall be coursed through the factory immediately for them to make the necessary adjustment and avoid any hassles for both parties. Since materials for unitized system shall be delivered, part of it, in components and not as an assembled unit(ladders), hauling of these materials would make it less complicated unlike for the assembled unit. UCW panels will be delivered and coordinated to the main contractor.

Prior to transporting the UCW and fabricated frames to the designated project site, a Delivery Receipt is prepared to allow the materials to be brought out from the plant to deliver it to the project site. All delivered materials will be inspected by QA/QC prior to endorsement to the main contractor /consultant (if necessary) for Materials Receiving Inspection.

6.4.1    GLASS

Glass panels (for Curtain wall) shall be delivered in two forms, a large quantity of glass maybe delivered in a wooden crate box, resting on A-frame, while lesser quantity maybe delivered just plainly resting on an A-frame with all necessary protection to prevent breakage.

6.4.2    ALUMINUM

Aluminum materials such as mullions, and other pertinent items that are cut in lengths shall be delivered using an open bed truck with wooden interlay at every layer to protect the aluminum from scratches and other unforeseen in-transit damages. Also, these materials shall be covered with AMG stickers as additional protection when delivered at site. Regular inspection report for the extrusion will be submitted to the main contractor /consultant.

6.4.3    SEALANT

Silicon sealant will be used in this project:

It will be checked in accordance with the specification. The “use by” date is clearly displayed on the product package.

Sealants delivered must have an expiration date of at least four (4) months from their delivery date.

6.5 MATERIALS INSPECTION AND STORAGE PROTECTION

6.5.1    MATERIALS INSPECTION

a)

            Subject          :           GLASS DELIVERY

            Location        :           AMG FACTORY

Dimension:

Check the height and width of all delivered glass. Refer to the official cutting list approved and signed. Dimension tolerance is ± 2mm.

Squareness:

Check the diagnosis of delivered glass. Square and rectangular glass should have equal diagnosis. Difference Tolerances are 6mm thick ±1.6mm; 8mm thick ±2mm.

Edge Defects:

Check the delivered glass for edge defects. Edge quality should be within the specified criteria.

Thickness:

Should comply with the approved shop drawing and structural calculations set by the Consultant.

Flaws:

Check glass for manufacturing flaws. The direction of glass ripples or waves shall be consistent and in conformance with Architectural design and Architect/Consultant visual acceptance criteria.

Inclusions:

Delivered glass should be free from inclusions. Laminated glass with visible bubbles or nickel sulfide stone in regular glass shall be out rightly rejected.

Scratches:

Check delivered glass from scratch.

Identification:

Each glass should have individual marks/tag for monitoring and identification purposes. Markings for Vision and Spandrel Glass should be readable inside and tower right corner.

Storing:

Should be placed where it would be protected from breakage and damage from effects of moisture including condensation of temperature changes and direct exposure to sunlight and other causes. It should also be easily accessed and properly identified.  Should be segregated on who comes first to be installed.

b)

Subject          :           ALUMINUM COMPOSITE PANELS

            Location        :           AMG FACTORY

Coating Color:

Check the color if it corresponds to the color sample which has been approved by the Consultant.

Thickness & Width:

Referred from the Purchase Order must be accurate and do comply the specifications.

Identification:

Each panel should have individual marks/tag for monitoring and identification purposes.

Storing:

Panels should be properly placed in a rack and tagged for easier access in materials sorting; Each bundle should have an individual packing list showing the content.

Bundles:

Packaging bundles should be checked if free from defects and damages that might occur during shipment/handling. Check quantity delivered against quantity declared as per packing list.

c)

Subject          :           SEALANT DELIVERY

            Location        :           AMG FACTORY

Shelf Life:

Delivered sealants should have a minimum of four (4) months prior to its expiration date.

Packaging conditions:

Boxes should be free from damage, intact and properly sealed.

Manufacturing references:

Manufacturing date/batch should be readable and remains in place.

Cartridges/Tubes:

Check cartridges/tubes conditions if free from dents and other defects.

Storing:

Sealants should be stored in a clean dry room with a temperature not more than 25 degrees centigrade.

d)

Subject          :           GASKETS/SETTING BLOCKS DELIVERY

            Location        :           AMG FACTORY

Extrusion quality:

Delivered gaskets should be in accordance with the approved list of materials and approved shop drawings.

Identification:

Boxes should be free from damage, intact and properly sealed.

Hardness:

Manufacturing date/batch should be readable and remains in place.

Storing:

Should be stored in a clean and dry room and properly placed in such a way that profiles should not be deformed or damaged.

e)

Subject          :           ALUMINUM PROFILES FABRICATED PANELS

            Location        :           AMG FACTORY

Powder Coating Finish:

Check coated material if it corresponds to the color sample which has been approved by the consultant.

Identification:

All delivered fabricated materials should have its own corresponding part number for easy sorting and assembly reference.

Storing:

Each type of fabricated materials should be placed in one rack and properly tagged for easier access in materials sorting/kit; the fabricated materials should be properly stored in a rack using a minimum 1-inch wooden spacer to avoid damaging any painted surfaces. Each crate should have an individual packing list showing the content of every crate or bundle.

Crates/Bundles:

Packaging crates or bundles should be checked if free from defects and damages that might occur during shipment/handling. Check quantity delivered against quantity declared as per packing list.

f)

Subject          :           FASTENERS

            Location        :           AMG FACTORY

Sizes and Finish:

Delivered fasteners should correspond to its specified ordered sizes and finish.

Mating Bolt, Nuts and Washers:

A random check should be done by mating delivered bolts, nuts, and washers as per materials or delivery markings/tagging.

Storing:

Fasteners should be stored as per sized and finished to easily access during materials distribution and stock monitoring.

g)

Subject          :           INSULATION AND FIRESTOPPER DELIVERY

            Location        :           AMG FACTORY

Packing:

Packing should be suitable enough to protect the material during delivery, any defects in the materials are considered unacceptable.

Thickness:

Should comply with the approved specification set by the consultant and shop drawings, this can also be referred to the Purchase Order; this type of material should remain dry until it is installed at site.

Storing:

Should be placed in a properly maintained store and free from moisture, if these materials become wet, they are no longer usable and no longer acceptable.

6.5.2    STORAGE PROTECTION

6.6 MATERIAL REJECTION AT PLANT

6.6.1    METHOD OF CONTROLLING AND STORING “REJECTED” MATERIALS:

6.6.2    SMALL REJECTION

6.6.3   IN-HOUSE REJECTION

6.7 FABRICATION, ASSEMBLY AND GLAZING

AMG will fabricate the Unitized Curtain Wall and Glass Façades in accordance with the specifications, approved shop drawings, and structural design calculations, using only skilled working team and proper methods and equipment. All parts of the glass façade should be identified after fabrication by piece marks clearly indicating their location on the building in conformance with the schedule shown on the approved drawings, then all elements on the glass façade, whether loose members or assembled unit, must be carefully packed to protect them from damage in transit and must be delivered to the job in accordance with the established schedule.

6.7.1   ALUMINUM FRAMES

6.7.1.1       MACHINING

All aluminum sections will be fabricated in accordance with the fabrication drawing issued. Cut sections will be marked with a part code for proper identification. Prior to any cutting, notching and drillings, aluminum sections will be provided with a plastic protective tape to avoid scratches. Worktables to be used are protected with rubber matting to avoid scratches on the aluminum sections.

6.7.1.2       INSPECTION / TOLERANCES

To define acceptable (manufacturing) tolerance, such as not specified in fabrication or submission drawings, procedural will apply to all fabricated parts or assembles that are produced by AMG or purchased.

In controlling the measure tape, the Quality Control will verify the accuracy of each tape received; against calibrated 100-cm straight edge of QA office. Tapes within 0.50 mm accuracy will be accepted. Tapes that do not meet these criteria shall be returned to vendor for replacement.

The following list of operations has been complied with the applicable tolerances, is as follows:

OPERATIONTOLERANCE
Saw Length+0, -0.50mm
Shear Size+0, -0.50mm
Squareness of Sheared sheet± 1 degree
Hole Size+0, -0.50mm
Hole Location+0, -0.50mm
Mill Cuts+0, -0.50mm
Bend Size+0, -0.50mm
Angularity (Bending Sheet Metal)± 1 degree
Radius Size+0, -0.50mm
Welded parts location+0, -0.50mm
Stud Weld Location+0, -0.50mm

6.8 GLASS BONDING AND GLAZING

Glass panes bonded to aluminum frames using the approved silicone (in the factory Bonding Area).

6.8.1   FINAL INSPECTION AND RELEASE

Visual inspection by QA/QC is necessary to check scratches on glass and aluminum section. If scratches are found, the product will not be released. Rectification procedure shall be submitted. Ensure that silicon is properly applied on the UCW panels and gaskets are accurately installed. Inspect the correctness of the code.

If the above complied the standard and is concurred by the aluminum system supplier, then the panel is ready for release.

6.9 PACKAGING/ DELIVERY / PROTECTION (UCW)

Fabricated items and other materials delivered to the project site are subject to inspection. Materials delivered are checked for proper palliating number and sequencing. Checked for proper protection of the panels and for scratches and damage.

DELIVERIES AND SITE ARRANGEMENTS:

1. Pallet for vertical support using the hoist.

2. Pallet for the vertical support using the tower crane.

(OFFLOADING USING THE TOWER CRANE)

(Steel Rack Frames)

(Platform Trolley) / (Flatbed Trailer)

TEMPORARY STORAGE at the SITE

All areas handover to AMG must be clear during installation and off-loading activities.

6.10 SITE INSTALLATION

6.10.1              GENERAL REQUIREMENTS

SUMMARY OF SITE REQUIREMENTS AND INSTALLATION PRE-REQUISITES

The site will require a lot of planning and coordination to prepare the site for panel installation. A meeting with the ABVRock team must be held to determine the location of the following sire requirements. All these activities must be organized to proceed with the preparation of the site.

The following activities will require the full cooperation of the main contractor before this statement can be applied.

6.10.2   SITE SURVEY AND SETTING OUT

6.10.3   BRACKET INSTALLATION

Brackets shall be designed for specific use according to location conforming to material specifications and approval.

The bracket shall be mounted at the soffit (or face) of slab and at the base floor to hold the aluminum framings and steel support framings using approved fasteners, where all fixings shall have tolerances in three directions; for in & out, elevation and lateral tolerances which shall be specified in the ITP.

6.10.4              UNITIZED CURTAIN WALL INSTALLATION

6.10.4.1     INSTALLATION PROCEDURES – UNITIZED CURTAIN WALL

6.10.4.2   UNITIZED SYSTEM INSTALLATION STARTER

The above will be repeated for the next panel, however, the male and female mullion must engage properly, and the gap based on the approved shop drawings must be respected.

The anchors for the adjacent units are positioned on the next pair or receiving brackets. It is set at the same line and level as the previous units. The unit is lowered into position and aligned with the gutter sleeve.

All corresponding units are set in the same manner.

The installation of panels will be done by 2 groups at two different locations at a time in a clockwise direction, depending on the sequence of installation. The sealer crew simultaneously do the sealing of gutter sleeves as the panels are installed. This will enable the gutters to dry and prepare the stack head for gutter testing prior to installation of panels above them by the next installation crew.

Some selected ACP locations shall remain open for ventilation purposes (based on the confirmation of the main contractor). After the glazing panels are all installed, the ACP for that certain location will then be installed through mechanical fixation.

In some areas where cladding projection exists, ACP will be installed either together with the glazing panels or separately by mechanical fixation.

The same procedure shall be implemented on the succeeding floors after AMG secured approval from the consultant to proceed.

One obstruction is the loading platform or the location of the construction hoist where the lifting operations of all trades are being carried-out, can also be utilized as initial drop off area upon lifting. AMG will coordinate with the project management team when the platform shall be relocated to a specific floor and location so that the panels will be installed.

6.11 CONTINUATION OF PANEL INSTALLATION UPON ALUMINUM SYSTEM SUPPLIER SECURING APPROVAL FROM THE CONSULTANT

6.12 DEGLAZING PROCEDURE

Prepare the glass for replacement and set it up on the designated floor. Once all the interior capping is removed, and exterior aluminum trims, start removing the sealant on interior face of the glass using utility knife and deglazing knife. Position the glass sucker in the center of the glass for both interior and exterior side. While holding the glass from the inside, remove the glass by tilting its sideways, slowly taking it inside the building. Place removed glass on the designated A-frame. Clean the perimeter of the aluminum with clean cloth. Remove sealant residue using spatula or knife and once again clean with a clean cloth. Remove all damaged gaskets and setting blocks. All items removed shall be clean thoroughly to ensure proper sealant adhesion.

6.13 INSTALLATION OF LOUVERS

6.14          REMOVAL OF PROTECTIVE FILMS 

Removal of the protective films from aluminum panels/frames shall be done as soon as possible or within 45 days after the installation to avoid the glue elements of protective film remaining on the surface of panel.

7. Inspection and Test Plan (ITP)

Refer to Section “18” (AMG – Quality Plan)

8. Plant and Equipment

8.1 CRADLE WORKING PLATFORM

Temporary Platform to be used for installation/rectification of light materials. The Third-party safety certification is a must prior to the installation of cradle working platform. (See sub-section 8.1.3)

8.1.1       SAFETY OPERATION REGULATION

8.1.2       DAILY CHECK

8.1.3       LOAD TESTING AND THIRD-PARTY CERTIFICATION

                                            (Basket/Cradle/Test Certificate)

8.2 MONORAILS

The Monorail is an essential requirement at the site to install the UCW panels. The Monorails Installation has agreed & done at site to install at the Roof with Main Contractor. Also, the Third-party safety certification is a must for the installed Monorails to prevent any future safety issues & confidence for the installed monorails.

Installed Monorail from our previous UCW project. For illustration only.

8.2.1                LOAD TESTING AND THIRD-PARTY CERTIFICATION

8.3 WINCH MOTOR with Required Length of Steel Rope

The Winch Motor will hang on the monorail with the required length of Steel rope. It will help to lift the Electrical Glass Sucker. Also, the Third-Party safety Certificate submitted to the Main Contractor.

Installed Winch Motor from our previous UCW project. For illustration only.

8.3.1       LOAD TESTING AND THIRD-PARTY CERTIFICATION

8.4 GLASS SUCTION (MANUAL AND ELECTRICAL)

Use to manually lift glazing for installation and shifting. (when panels/items are not too heavy to handle)

(Electrical Glass Sucker – Use to lift heavy panels/items and when manual lifting is not easy)

8.5            WELDING MACHINE (For hot works)  

Hot works may be applied if welding and grinding are needed.

9. SPECIAL SCAFFOLD / ACCESS EQUIPMENT

10. Training and Competency Personnel

All heavy operators such as but not limited to Mobile crane, Manlift, working under AMG supervision require valid certifications testifying to their competency. Copies of all documents are available upon request. Any hired drivers or operators shall comply with these guidelines.

11. First Aid and Emergency Arrangements (Including fall arrest)

11.1 PROVISION OF FIRST AID FACILITIES

11.2          PERSONAL PROTECTIVE EQUIPMENT

12. Advised Any Permits to Work Required (Hot works, Confined spaces, Excavation, Electrical)

The Work Permit System incorporates procedures commonly used in industrial facilities to ensure that necessary communication takes place and hazards are controlled.

AMG erection activities do not require a long period of welding and cutting activities; thus, it is based as per scope of work. However, in such cases in any heat producing activities are involved, we may be using the main contractor’s standard hot work permit as an important tool in maintaining a safe work environment whenever it is required in a restricted area.

13. Environmental Considerations

Not applicable.

14. Waste Management

Will be carried out in accordance with the main contractor’s Waste Management Plan.

15. Hazardous Substances –

Not applicable.

16. Any Special Storage Requirements

Storeroom for Special Tools (Power Tools and Hand Tools) to be used for installation of Curtain Wall and other Façade works.

17. Testing and Commissioning

18. Supporting Documents